Brief information up to 01.08.2017
Total cost of the project:– 8 600 000 USD
European Bank for Reconstructon
and Development (Credit) - 3 900 000 дол.США
Contribution of the Government of
the Republic of Tajikistan - 4 700 000 USD
Disbursement from the
beginning of the project: - 6 288 000USD (73,1%)
Beginning of the project: April 2013
Completion of the project: April 2017
Consultant: “Luis Berger” (UK)
Project description: Reconstruction and technical re-equipment of Khujand International Airport
April 22, 2013 – signing of the Credit agreement between “Khujand International Airpot”, JCS and European Bank for Reconstruction and Development on the support of the project “Credit for Khujand International Airport”,
April 30, 2013 – signing of the direct agreement between Republic of Tajikistan and and European Bank for Reconstruction and Development on the support of the project “Credit for Khujand International Airport”,
May 16, 2016 – with participation of specialists of Ministry of Transport, representatives of World Bank, Asian Development Bank, European Bank for Reconstruction and Development and Japan International Cooperation Agency was held a presentation of master plan of Khujand International Airport,
May 20, 2016 – signing of the contract between “Khujand International Airport”, JCS and “Radar-Ga” for purchase and installation of lighting navigational aids and radiotechnical equipment DME/N,
June 12, 2017 – “Systems Interface” (UK) was defined as a winner of the tender for devivery and installation of takeoff and landing system ILS.