Brief information up to 01.02.2016
- Total cost – USD 71,992 million;
• the credit Eximbank China – 56,994 million a dale. USA
• a contribution SUE Roji ojani Tochikiston – 2,999 million a dale. USA
- contractor: china railway 19 bureau group (China)
- beginning of the project - May 2015, end of the project - August 2016
- description of the project: construction of 5 bridges with 712 m length and 3 tunnels of 3755 m length
- the mastered all-design sum – 18,898 million a dale. USA (26%)
- number of the personnel – 552 people: the local – 329ch. (60%), foreign – 223ch. (40%)
- quantity of the equipment and equipment – 112 units
- 07.11.2014 - signing of the Loan Agreement between Government of the Republic of Tajikistan and Eximbank (China)
- works in a tunnel No. 1 from an entrance and an exit are conducted, in a tunnel No. 2 from an entrance and in tunnel No. 3 from an exit.
- the working draft of bridges No. 1, 2 and 3 are handed over in examination.
- construction works are ongoing on bridges No. 1, 2, 3 and 4 and preparatory works - on the bridge No. 5.
- working drafts of bridges No 1, 2 and 3 are approved by Gosexpertiza. Workinf drafts for bridges No 4 and 5 are submitted to Gosexpertiza.