Brief information up to 01.08.2017
|
Total cost of the project: |
- 92 900 000 USD |
|
Islamic Bank for Development (Credit) |
- 20 000 000 USD |
|
Saudi Fund for Development (Credit) Kuwait Fund for Arab Economic Development (Credit) Abu Dhabi Fund for Development (Credit) OPEC Fund (Credit) Contribution of the Government of the Republic of Tajikistan |
- 20 000 000 USD - 17 000 000 USD
- 15 000 000 USD - 13 000 000 USD - 7 900 000 USD |
|
Disbursement from the beginning of the project: |
- 79 567 000USD (85,6%) |
Beginning of the project: January 2011
Completion of the project: December 2017
Consultant of the project: JV Al-Abdulhadi (Kuwait) and Spectrum (Lebanon)
Contractor of the project: JV Kombaynd Group (Kuwait) and Tekar (Turkey)
Project description:
- construction of 40 km of road,
- construction of 10 bridges,
- purchase of the equipment for road maintenance.
Number of staff: total – 407persons
local – 371 persons (91%)
foreigners – 36 persons (9%)
Number of equipment – 190items.